- Leasehold data
- Tower Hamlets
- Chime Properties
- LON/00BG/LAM/2025/0012, LON/00BG/LRM/2025/0015, LON/00BG/LSC/2024/0266
Blocks B, C, D Maltings Close, London E3 3TE
A right to manage, service charges, appointment of manager decision of the First-tier Tribunal (Property Chamber), issued on 22 September 2025 in case LON/00BG/LAM/2025/0012, LON/00BG/LRM/2025/0015, LON/00BG/LSC/2024/0266. Chime Properties Limited was the respondent landlord.
Data updated
- Case reference
- LON/00BG/LAM/2025/0012, LON/00BG/LRM/2025/0015, LON/00BG/LSC/2024/0266
- Decided
- 22 September 2025
- Case type
- Right to manage, Service charges, Appointment of manager
- Tribunal region
- London
- Landlord
- Chime Properties Limited (respondent landlord)
- Postcode
- E3 3TE, Tower Hamlets
- Length of decision
- 23 pages
The case in brief
The case began when Maltings Close Residents Management Company Limited asked the tribunal to decide whether the leaseholders could take over management of the building, in March 2025. On the other side was the landlord, Chime Properties Limited.
The decision is dated 22 September 2025. That was 6 months after the application.
Written from the published decision and public registers.
What the tribunal was asked
The application, as the tribunal recorded it: “Application in relation to the denial of the Right to Manage.”
What this kind of case is
A right to manage case. Leaseholders can take over the management of their building through a right to manage company, and the tribunal decides disputes about whether they are entitled to.
A service charge case. Leaseholders or landlords can ask the tribunal whether service charges are payable and reasonable, under the Landlord and Tenant Act 1985.
An appointment of manager case, where the tribunal is asked to appoint a manager to run the building in place of the landlord.
General law, not a summary of this decision. Most lease extensions are agreed without going to the tribunal.
How this case compares
It was one of 29 right to manage decisions the tribunal published in 2025 across England and Wales, and one of 17 from its London office. We hold 219 published right to manage decisions in all, 1 of them naming Chime Properties.
Time from application to decision
- This case: 6 months
- Typical at the London office: 4 to 8 months, median 5
Middle half of 42 right to manage decisions whose application date we could read from the decision.
How long the case took
6 months from the application to the decision.
- 26 March 2025 Counter-notice served
- 26 March 2025 Application made to the tribunal
- 22 September 2025 Decision issued
Dates as stated in the published decision.
The building
- Building
- Multiple residential accommodation
- Homes in the building
- 57
- Floors
- 7
- Height
- 26 m
- Built
- 2007
- Roof
- Waterproof membrane or concrete
Ordnance Survey building survey data (OS NGD Buildings), for the main building at E3 3TE.
Leases at E3 3TE
HM Land Registry holds registered leases for 57 flats at E3 3TE. 0 have under 80 years left, when extending starts to cost more because marriage value is added.
Appeal cases cited
Legislation referred to
- Landlord and Tenant Act 1987
- Commonhold and Leasehold Reform Act 2002
- Tribunal Procedure (First-tier Tribunal) (Property Chamber) Rules 2013
Key terms
Read the decision
For the tribunal's reasoning in full, read the decision as published by the tribunal on GOV.UK.
Related pages
More decisions involving Chime Properties
- WestBrook Court, 472, Christchurch Road, Bournemouth, BH1 4BD Section 20 dispensation 2026
- 1 DANBY FOLD, RAINHILL, PRESCOT, MERSEYSIDE, L35 9LY Enfranchisement costs 2020
- Flat 24 Barnes House, John Williams Close, London SE14 1 QW Lease extension costs 2019
All 4 decisions and the full Chime Properties profile
Source: First-tier Tribunal (Property Chamber) decisions published on GOV.UK and BAILII. How we build these pages.